Survey / Resurvey - Physical Progress

State/UT
District * Tapi
Tehsil * Vyara
Status Entry Done 18/07/2018
Name of Agency undertaking the Survey Work WAPCOS LTD

Area Details

Rural(Sq Km) 407.463
Urban(Sq Km) 0.425
Forest(Sq Km) 33.669
Net Area(Sq Km) 441.557

Survey Details

Year Of Last Survey Carried Out 2012-2013
Status of present survey * Ongoing
Whether Survey being done using Departmental Staff or Private Agency? * Private Agency

Ground Control Point(GCP)

Ground Control Point Setup to facilitate Survey/Resurvey * Yes
Category of GCPs Total No of GCPs Actual Adopted Dimensions Standard Dimensions
Primary 582 1 * 1 Sq Km 16 * 16 Sq Km
Secondary 46 4 * 4 Sq Km 4 * 4 Sq Km
Tertiary 3 16 * 16 Sq Km 1 * 1 Sq Km
Number of Villages Where Ground Control Point Established 92
Whether Validated with Reference to the Survey of India’s GCP * No
Total no of Villages 94
Total No Surveyed villages 92
Total No villages In-Progress 0
Area Surveyed (Sqkm) 407.463
Likely Date of Finishing the Work (MM/dd/yyyy) Jul 18, 2018

Technology Used for surveying

GPS + ETS (Ground Method)
Remarks
Number of Villages Where Revenue Maps Generated 92
Number of Villages Where Ground Truthing have been done 62
Number of Villages where Final Promulgation Done 58
Any other related Information(Challenges faced if any)