S.No. Village Name Total No. of ROR Total No. of Land Owners/ Holders ROR Data Entry as of Previous settlement (100% checked and frozen) Availability of ROR Distribution/Printing Software ROR Linkage With Aadhaar No. of Land Owners/ Holders whose ROR is linked with Aadhaar Whether Mutation notice and Mutation Workflow are Computerized Issuance of Digitally Signed ROR Status Entry Date
Completed Ongoing Not Started
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
1 Ekhao 116 96 Completed Not Done 0 0 116 0 Not Done Not Done 2019-08-13
2 Kingniu 230 152 Completed Not Done 0 0 0 0 Not Done Not Done 2019-08-13
3 Lengnyu 351 285 Completed Not Done 0 0 0 0 Not Done Not Done 2019-08-13
4 Pathso 637 516 Completed Not Done 0 0 0 0 Not Done Not Done 2019-08-13
5 Pathso Nokeng 450 397 Completed Not Done 0 0 0 0 Not Done Not Done 2019-08-13
6 Tsangkoi (UR) 58 56 Completed Not Done 0 0 58 0 Not Done Not Done 2019-08-13
7 Tsuwao 210 160 Completed Not Done 0 0 210 0 Not Done Not Done 2019-08-13
8 Yokao 268 252 Completed Not Done 0 0 268 0 Not Done Not Done 2019-08-13