CLR (Computerization of Land Records) - Physical Progress

State/UT: ANDHRA PRADESH
District: Tirupati
Tehsil Name: Pichatur
S.No. Village Name Total No. of ROR Total No. of Land Owners/ Holders ROR Data Entry as of Previous settlement (100% checked and frozen) Availability of ROR Distribution/Printing Software ROR Linkage With Aadhaar No. of Land Owners/ Holders whose ROR is linked with Aadhaar Whether Mutation notice and Mutation Workflow are Computerized Issuance of Digitally Signed ROR Status Entry Date
Completed Ongoing Not Started
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
1 Appambattu 554 333 Completed Done 554 0 0 314 Done Done 2024-07-30
2 Chilamathur @ Bangala 2226 465 Completed Done 2226 0 0 392 Done Done 2024-07-30
3 Karuru @ Krishnagiri 2393 680 Completed Done 2393 0 0 619 Done Done 2024-07-30
4 Keelapudi 1249 383 Completed Done 1249 0 0 333 Done Done 2024-07-30
5 Mudiyur 2047 700 Completed Done 2047 0 0 612 Done Done 2024-07-30
6 Neervoy 1390 331 Completed Done 1390 0 0 283 Done Done 2024-07-30
7 Pichatur 2250 476 Completed Done 2250 0 0 405 Done Done 2024-07-30
8 Pulikondram 1968 395 Completed Done 1968 0 0 349 Done Done 2024-07-30
9 Pulipadu @Govardhanagiri 1383 369 Completed Done 1383 0 0 320 Done Done 2024-07-30
10 Rajanagaram 148 90 Completed Done 148 0 0 20 Done Done 2024-07-30
11 Ramagiri 1937 356 Completed Done 1937 0 0 295 Done Done 2024-07-30
12 Ramapuram 1811 410 Completed Done 1811 0 0 335 Done Done 2024-07-30
13 Reppalapattu 122 47 Completed Done 122 0 0 36 Done Done 2024-07-30
14 Shamsheer Bahadurpeta 2296 442 Completed Done 2296 0 0 394 Done Done 2024-07-30
15 Sivagiri 1835 435 Completed Done 1835 0 0 392 Done Done 2024-07-30
16 Velur 1184 227 Completed Done 1184 0 0 199 Done Done 2024-07-30
17 Vengalathur 3193 687 Completed Done 3193 0 0 610 Done Done 2024-07-30