CLR (Computerization of Land Records) - Physical Progress

State/UT: SIKKIM
District: NAMCHI DISTRICT
Tehsil Name: Lingmoo
S.No. Village Name Total No. of ROR Total No. of Land Owners/ Holders ROR Data Entry as of Previous settlement (100% checked and frozen) Availability of ROR Distribution/Printing Software ROR Linkage With Aadhaar No. of Land Owners/ Holders whose ROR is linked with Aadhaar Whether Mutation notice and Mutation Workflow are Computerized Issuance of Digitally Signed ROR Status Entry Date
Completed Ongoing Not Started
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
1 Kolthang 435 435 Completed Done 0 0 435 0 Done Not Done 2024-06-14
2 Lingmoo 150 150 Completed Done 0 0 150 0 Done Not Done 2024-06-14
3 Mangzing 311 311 Completed Done 0 0 311 0 Done Not Done 2024-06-14
4 Nehbrum 469 469 Completed Done 0 0 469 0 Done Not Done 2024-06-14
5 Pepthang 159 159 Completed Done 0 0 159 0 Done Not Done 2024-06-14
6 Tokday 416 416 Completed Done 0 0 416 0 Done Not Done 2024-06-14