Modern Record Room (MRR) - Physical Progress

State/UT: HIMACHAL PRADESH,
S.No. District Name No. of Tehsils
No. of Modern Record Rooms
Sanctioned Completed Ongoing Completed Civil Works Procured Equipment
No. % No. %
(1) (2) (3) (4) (5a) (5b) (6a) (6b) (7) (8)
Grand Total 188 117 86 73.5% 13 11.11% 88 77
1 BILASPUR 7 6 6 100.00% 0 0.00% 2 2
2 CHAMBA 14 10 10 100.00% 0 0.00% 7 6
3 HAMIRPUR 12 8 8 100.00% 0 0.00% 0 0
4 KANGRA 40 10 9 90.00% 0 0.00% 10 10
5 KINNAUR 7 6 2 33.33% 4 66.67% 3 3
6 KULLU 9 8 7 87.50% 0 0.00% 8 8
7 LAHUL AND SPITI 3 3 1 33.33% 2 66.67% 3 3
8 MANDI 31 25 24 96.00% 0 0.00% 24 24
9 SHIMLA 26 10 6 60.00% 2 20.00% 7 7
10 SIRMAUR 14 10 8 80.00% 0 0.00% 8 8
11 SOLAN 13 9 4 44.44% 5 55.56% 4 4
12 UNA 12 12 1 8.33% 0 0.00% 12 2